Also serving the communities of De Luz, Rainbow, Camp Pendleton, Pala and Pauma

Mission Road update

FALLBROOK — The new intersection at Main Avenue and Mission Road is now open.

During the month of December, Daley Construction is conducting the following activities during the hours of 7 a.m. and 4 p.m. Monday through Friday. During the daytime work, one lane of traffic in each direction and one two-way left turn lane will be kept open.

• Begin the following improvements on the west side of Mission Road from Clemmens Lane to Almond Street: drainage, retaining walls, sidewalk, curb and gutter

• Complete underground conversion trenching and start underground utility work

Temporary traffic contr...

 

Reader Comments(0)

 
 
Rendered 11/09/2024 19:55