Also serving the communities of De Luz, Rainbow, Camp Pendleton, Pala and Pauma

Time extension approved for Live Oak Park Road subdivision

The San Diego County Board of Supervisors approved a time extension to complete infrastructure improvements for a 58.03-acre subdivision along Live Oak Park Road.

The supervisors’ 5-0 vote September 15 extends the performance completion date from September 18, 2010, to September 18, 2012. The completion date is when streets, drainage, and water facilities must be completed; the residential units themselves do not need to be completed by that deadline. The ownership must also substitute the current lien contract with adequate security to ensure completion of the infrastructure and payment for l...

 

Reader Comments(0)

 
 
Rendered 11/18/2024 11:34