FPUD approves change order for Rattlesnake Reservoir re-coating

A change order to the Fallbrook Public Utility District's (FPUD) contract with Simpson Sandblasting for re-coating Rattlesnake Reservoir was approved on a 5-0 FPUD board vote April 27.

The change order adds $75,200.86 to the original $457,740 contract to bring the total amount to $532,940.86 and covers additional tasks determined to be needed after an inspection of the emptied tank discovered existing interior corrosion.

"It's additional work to complete the refurbishment," said FPUD general manager Brian Brady.

FPUD has a planned maintenance program which re-coats the interior and exterior of...

 