An additional change to the contract to re-coat Rattlesnake Reservoir has added $60,226.12 to the project contract and extended the completion date to Aug. 30.
A 5-0 FPUD board vote July 27 approved the amendment to the contract with Simpson Sandblasting and Specialty Coatings, Inc. The total contract amount was increased from $532,940.86 to $593,166.98 while 14 days were added to the previous Aug. 16 final completion date.
FPUD budgeted $600,000 for the project. "Even with the additional work it still came under the engineer's original estimate," said FPUD general manager Brian Brady.