CWA approves Valley Center Pipeline expansion change orders

The San Diego County Water Authority board approved change orders to the SDCWA's contract with NEWest Construction Company, Inc., for the Twin Oaks Valley Water Treatment Plant Expanded Service Area project.

The September 24 CWA board vote accepted three change orders totaling $315,145 which had been authorized by CWA staff under the authority of CWA general manager Maureen Stapleton while also authorizing Stapleton to execute an additional change order for $93,392. The $400,537 change order amount increases the total contract amount to $4,090,537.

A change order for $282,599 includes the repl...

 