FPUD approves change order in valve replacement

The Fallbrook Public Utility District (FPUD) board approved a change order in FPUD's valve replacement project while also approving a notice of completion.

FPUD staff worked with TK Construction on the additional work to ensure that the project would be finished by the May 25 scheduled completion date. The work was completed ahead of schedule and on May 23 the FPUD board voted 5-0 both to approve the notice of completion and to approve the change order, which increased the contract amount from $347,771.89 to $374,236.63.

"The contract was to replace major valves in the system," said FPUD gener...

 